No |
Name of work |
DURATION |
Cost (Million VND) |
Employer |
---|---|---|---|---|
I |
Railway projects |
|||
1 |
Study, design and manufacture of facilities for AWS (automatic warning system) level crossings |
2000¸2004 |
5,000 |
Vietnam Railways |
2 |
Establishment of feasibility study for Signal- Telecommunication Modernization Project for northern railway lines, Hanoi junction and Vinh - Nha Trang section |
2001¸2004 |
5,000 |
Vietnam Railways |
3 |
Survey, construction design for track, station, architecture and culvert on Hanoi - Ho Chi Minh City Railway Line |
1996¸2005 |
20,000 |
Vietnam Railways |
4 |
Survey, establishment of feasibility study, construction design of items in “Railway Infrastructure Strengthening Project in Central Region from Quang Binh to Khanh Hoa” |
1998¸2005 |
8,000 |
Vietnam Railways |
5 |
Survey, establishment of feasibility study, construction design of Yen Xuan Bridge on Hanoi - Ho Chi Minh City Railway Line |
1998¸2005 |
3,000 |
Vietnam Railways |
6 |
Survey and construction design of level-crossing system on Hanoi - Ho Chi Minh City Railway Line |
2001¸2005 |
6,500 |
Vietnam Railways |
7 |
Survey, establishment of feasibility study and detailed design for Yen Vien - Pha Lai - Ha Long - Cai Lan Railway Line Project |
2001¸2006 |
25,000 |
Vietnam Railway Authority |
8 |
Survey, establishment of feasibility study and detailed design for Hanoi - Ho Chi Minh City Railway Line Bridges Safety Improvement Project on Hanoi – Hochiminh City Railway Line |
2002¸2006 |
30,000 |
Vietnam Railways |
9 |
Establishment of pre-feasibility study and feasibility study for Hanoi - Hai Phong Railway Electrification Upgrading Project |
2004¸2006 |
8,000 |
Vietnam Railways |
10 |
Survey and shop drawing design for strengthening railway at Hai Van Pass |
2004¸2006 |
2,200 |
Vietnam Railways |
11 |
Survey, establishment of feasibility study, detailed design for rehabilitation of remaining weak bridges on Hanoi - Ho Chi Minh Railway Line |
2007¸2010 |
34,000 |
Vietnam Railways |
12 |
Preparation of pre-feasibility study for Mu Gia - Tha Khet railway |
2007¸2008 |
2,200 |
Vietnam Railway Authority |
13 |
Survey and preparation of feasibility study for Khe Net Pass Railway Rehabilitation Project |
2007¸2009 |
2,000 |
Vietnam Railways |
14 |
Construction planning of intersection system between railway and roadway in Vietnam railway network |
2008¸2009 |
3,400 |
Vietnam Railway Authority |
15 |
Inventory and inspection of breach positions for right-of-way of North railway lines |
2008¸2009 |
5,000 |
Vietnam Railways |
16 |
Establishment of investment report of North - South High Speed Railway Project (in association with Japanese consultants) |
2008¸2010 |
56,000 |
Vietnam Railways |
17 |
Safety Corridor Order Restoration Project for Railway Lines according to Decision 1856 of Prime Minister (Phase 2) |
2009¸2010 |
45,000 |
Vietnam Railways |
18 |
Survey and construction drawing design of Binh Dinh - Khanh Hoa railway consolidation according to the urgent command |
2010 |
7,000 |
Vietnam Railways |
19 |
Establishment of feasibility study of Hanoi - Ho Chi Minh Railway Line Weak Tunnel Rehabilitation Project |
2010 |
6,900 |
Vietnam Railways |
20 |
Survey, construction drawing design for strengthening 2 collapsed sections on Yen Vien - Lao Cai Railway Line |
2010-1011 |
2,000 |
Vietnam Railways |
21 |
Finalization of Detailed design of Yen Vien - Lao Cai Railway Upgrading Project |
2011 |
2,900 |
Vietnam Railways |
22 |
Survye, construction drawing design of work items under plan 1856, Phase 2 according to the urgent command |
2012 |
3,500 |
Vietnam Railways |
23 |
Survey, establishment of feasibility study of Hai Phong International Gateway Port Access Rail Link |
2012 |
10,500 |
Vietnam Railway Authority |
24 |
Survey, evaluation of existing status, audit and verification of railway lines at apatite mines, Lao Cai Province |
2012 |
1,600 |
Vietnam Apatite Limited Company |
25 |
Verification of Sai Gon - Loc Ninh Railway Construction Project |
2012 |
1,700 |
Vietnam Railway Authority |
26 |
Verification of Bien Hoa - Vung Tau Railway Construction Project |
2013 |
1,670 |
Vietnam Railway Authority |
27 |
Investigation, construction drawing design of Package CP1A under Hanoi - Ho Chi Minh Railway Line Bridge Safety Improvement Project |
2012-2013 |
2,550 |
Vietnam Railways |
28 |
Construction drawing design of Yen Vien - Lao Cai Upgrading Project |
|
|
Vietnam Railways |
- |
Package CP2 |
2011 |
8,000 |
|
- |
Package CP3 |
2013 |
6,900 |
|
- |
Package CP1 |
2013 |
2,900 |
|
29 |
Survey, establishment of economic-technical report on improving, repairing, upgrading legal level crossing but violating level crossing rules |
2013 |
11,800 |
Vietnam Railways |
30 |
Adjustment of Project: Railway Signal and Telecommunication System of Hanoi – Vinh section on Hanoi – Hochiminh City Railway Line, Phase II |
2013 |
2,000 |
Vietnam Railways |
31 |
Survey, Preparation of Feasibility Study, Construction Drawing Design for Repair, Improvement, Upgrade of Passenger Platforms at Hanoi and Sai Gon Stations on Hanoi - Ho Chi Minh City Railway Line |
2014 |
2,000 |
Vietnam Railways |
32 |
Improvement of 10 stations: Ca Na, Song Mao, Song Luy, Suoi Van, Trang Tao, Bao Chanh, Long Khanh, Dau Giay, Trang Bom, Ho Nai on Nha Trang - Ho Chi Minh City Railway Section |
2014 |
1,990 |
Vietnam Railways |
33 |
Formulation of Feasibility Study for Hanoi – Ho Chi Minh City Railway Line Bridges Safety Improvement Project, Phase II |
2014 |
11,820 |
Ministry of Transport |
34 |
Formulation of Feasibility Study for “Railway Signal & Telecommunication System Modernization Project on Vinh- Ho Chi Minh City section of Hanoi- Ho Chi Minh City Railway Line, Phase 2” |
2014 |
11,210 |
Ministry of Transport |
35 |
Formulation of feasibility study and construction drawing design of repair and rehabilitation of erosion protection in the southern railway section of Yen Xuan Bridge Km 331 + 111 |
2014 |
1,380 |
Vietnam Railways |
36 |
Construction drawing design of CP3B, CP3C of Hanoi – Hochiminh City Railway Line Bridge Safety Improvement Project |
2014 |
3,880 |
Railway Construction Joint Stock Company |
37 |
Survey, Preparation of Construction Drawing Design and Cost Estimate for Long Bien Bridge Rehabilitation Project, Phase I |
2015 |
4,840 |
Railway Project Management Unit of Region 2 |
38 |
Survey, Evaluation of Existing Status, Preparation of Cost Estimate and Project Proposal for “Transfer of Operation Right of Da Lat – Da Tho Railway Section” |
2015 |
1,530 |
Bach Dang Complex Company |
39 |
Formulation of Project Proposal for Hanoi – Hai Phong (Hai Phong International Gateway Port) 1435mm-gauge Railway Construction Project in PPP form |
2015 |
970 |
IMP-ITD Joint-venture |